Ghar ki foundation ke liye — PCC bed aur footing — cement bags, reti, aggregate aur ₹ cost, m ya ft mein।

इनपुट

इकाई प्रणाली

Footing ke neeche levelling course (aksar 75–150 mm)।

परिणाम

Kul concrete volume

1.98

Kul concrete volume

69.92cft

Volume breakdown

Footing volume

1.62

PCC bed volume

0.36

50 kg cement bags

15bags

Reti required

29.90cft

Aggregate required

59.80cft

Material cost ka anuman

₹10,934

गणना कैसे होती है

सूत्र

  1. Imperial ho to ft → m convert
  2. footing_volume = length × width × footing_depth
  3. pcc_volume = length × width × pcc_thickness
  4. footing_volume ko selected grade ratio se split → cement, reti, aggregate
  5. pcc_volume ko M10 ratio se split → cement, reti, aggregate
  6. Cement volumes combine karein → bags; reti/agg combine → cft (× 35.3147)
  7. cost = bags × ₹/bag + (reti_cft + agg_cft) × ₹/cft

मान्यताएँ

  • Foundation ko PCC bed + footing maana — dono length × width rectangles.
  • Sabhi dimensions ke liye Metric (m) ya Imperial (ft) chunein।
  • PCC (levelling) bed hamesha M10 (1:3:6) — footing aapke selected grade se।
  • Material split har layer ke liye grade mix aur dry volume × 1.54 se।
  • Cement bags 50 kg standard Indian bags, PCC + footing combined।
  • Cost = (cement bags × ₹/bag) + ((reti + aggregate) cft × ₹/cft)।
  • Excavation, steel, formwork, mazdoori shamil nahi — grade aur depth structural drawing se confirm karein।